LA SEWERS


CITY OF LOS ANGELES
DEPARTMENT OF PUBLIC WORKS

Search
Advanced
ABOUT THE CITY'S SEWER SYSTEM
CURRENT SEWER CONSTRUCTION PROJECTS
FUTURE SEWER CONSTRUCTION PROJECTS
Alvarado Crandall Relief Sewer
Buchanan Relief Sewer
Central Area Cement Sewer Renewal Program Unit 6
Central Outfall Sewer Rehabilitation Project
MAZE 5 Sewer Rehabilitation Project
The Secondary Sewer Renewal Program (SSRP)
Muirfield Road and Olympic Blvd. Sewer Rehabilitation Project
  Roscomare Road and Stradella Road Sewer Rehabilitation Project
  Veteran Avenue and Sunset Boulevard Sewer Rehabilitation Project
COMPLETED SEWER CONSTRUCTION PROJECTS
LATERAL ROOT NOTIFICATION PROGRAM
FATS, OIL AND GREASE PROGRAM
SPILLS & BACKWATER VALVES
ODORS

 
Project Information from the Bureau of Engineering

City Sewers Future Construction

Buchanan Relief Sewer

The City of Los Angeles Department of Public Works will soon begin construction on a sewer project in a portion of Eagle Rock. The Buchanan Relief Sewer will provide additional capacity and prevent spills in this area. The project will be built by placing the new pipes in trenches dug in the streets. The City will make every effort to minimize disturbances to this neighborhood.


CONSTRUCTION FACTS

  • Construction method: open trench
  • Construction period: November 2007 – December 2008
  • 3,100 linear feet of 18” diameter sewer
  • Project cost: $2.8 million
  • Work will take place on portions of Lincoln Ave. , Ave. 54, Buchanan St. , and Ave. 56
  • Twelve new maintenance holes will be built
  • Construction will generally take place Monday through Friday, from 7:00 a.m. until 4:00 p.m.
  • Some service interruptions may take place when the residential sewers are reconnected to the new sewer – residents will be notified 24 to 48 hours in advance
  • Traffic and parking controls will be in effect - parking signs will be posted and flaggers will be used where traffic is impacted
  • Safe and adequate pedestrian and vehicle access will be maintained at all times to residences, businesses and fire hydrants
  • Each trench will be completed in 10 to 12 business days Trash pickup, deliveries, access to businesses and residential driveways will be maintained

 

 

CONTACT  AND  INFORMATION
Report Sewer ODORS
Report Sewer SPILLS   Or CALL 311, or (213) 473-3231
More information: (213) 978-0333,
or email pao@lacity.org
City of Los AngelesDepartment of Public Works  BUREAU OF SANITATION
 BUREAU OF ENGINEERING
 CONTRACT ADMINISTRATION