Sunset Boulevard and Amalfi Drive Sewer Rehabilitation Project
This sewer pipe rehabilitation project began in March 2008. The project is located in Brentwood and Pacific Palisades. The approximate boundary of the project is Romany Drive on the north, Beckwith Avenue on the east, Chautauqua Boulevard on the west, and Channel Lane on the south.
QUICK FACTS
- About 3.3 miles of sewer pipes ranging from 8 inches to 15 inches in diameter will be rehabilitated or removed and replaced.
- new maintenance holes will be installed.
- Construction period: February 2008 through early 2010.
- Construction will generally take place Monday through Friday, from 7:00 a.m. until 5:00 p.m.
- Estimated Cost: $2,243,000.
- Construction methods will include sewer pipe lining (rehabilitates defective sewers without excavation and surface disruption), and sewer pipe removal and replacement (performed by “open cut” or trenching, a method that is typically used where sewers are shallow).
- In order to minimize disruption on your street, most of the construction work at each location will be completed in about 5-10 business days.
- Trucks and other equipment such as pipes will be used during construction, and you may see open trench excavation and debris removal.
- Dust control will be provided in all project areas.
- Enclosures or other barriers will be used in construction areas wherever necessary for public safety.
- Flaggers will be used where traffic is impacted. Traffic will be restored to normal when construction has been completed at the end of each workday.
- Trash pickup, deliveries, access to businesses and residential driveways will be maintained.
- Parking may be temporarily restricted in some areas, and signs will be posted in advance telling you where and when.
- You will be notified 24-48 hours in advance whenever sewer services may be temporarily interrupted.
|