LA SEWERS


CITY OF LOS ANGELES
DEPARTMENT OF PUBLIC WORKS

Search
Advanced
ABOUT THE CITY'S SEWER SYSTEM
CURRENT SEWER CONSTRUCTION PROJECTS
  Air Treatment Facility - La Cienega and Jefferson
  Alvarado Crandall Relief Sewer
  Avenue 45 – Arroyo Drive Relief Sewer
  Buchanan Relief Sewer
  Hollydale Drive Local Sewer Addition Project
  Lower North Outfall Sewer Rehabilitation Project –Phase 2
  North Broadway Sewer Rehabilitation Project (includes Chinese version)
Silver Lake Area Sewer Replacement Project
  Upper Beachwood Central Maintenance Hole Addition Project
Scroll Scroll list below to select an SSRP project.
FUTURE SEWER CONSTRUCTION PROJECTS
LATERAL ROOT NOTIFICATION PROGRAM
FATS, OIL AND GREASE PROGRAM
SPILLS
ODORS
HELP PROTECT THE ENVIRONMENT

 
Project Information from the Bureau of Engineering

City Sewers Current Construction

Olympic Boulevard and Spaulding Avenue Sewer Project

This sewer pipe rehabilitation project began in April 2008 in the Wilshire District. The approximate boundary of the project is Beverly Blvd. on the north, La Brea Blvd. on the east, La Cienega Blvd. on the west, and Pico Blvd. on the south.


QUICK FACTS

  • About 2.8 miles of 8 and 10-inch sewer pipes are being rehabilitated, or removed and replaced.
  • One new maintenance hole is being installed.
  • Construction period: April 2008 through late winter/early spring 2008-2009. Weather or other circumstances could shift the work schedule.
  • Construction generally takes place Monday through Friday, from 7:00 a.m. until 4:00 p.m., and on major streets from 9:00 a.m. until 3:00 p.m.
  • Estimated Cost: $1.1 million.
  • Construction methods include sewer pipe lining (rehabilitates defective sewers without excavation and surface disruption), and sewer pipe removal and replacement (performed by “open cut” or trenching, a method that is typically used where sewers are shallow).
  • In order to minimize disruption in the streets, most of the construction work at each location is being completed in about 5-10 business days.
  • Trucks and other equipment such as pipes are being used during construction, and you may see open trench excavation and debris removal.
  • Dust control is being provided in all project areas.
  • Enclosures or other barriers are being used in construction areas wherever necessary for public safety.
  • Flaggers are being used where traffic is impacted. Traffic will be restored to normal when construction has been completed at the end of each workday.
  • Trash pickup, deliveries, and access to businesses and residential driveways are being maintained.
  • Parking may be temporarily restricted in some areas, and signs will be posted in advance telling you where and when.
  • You will be notified 24-48 hours in advance whenever sewer services may be temporarily interrupted

CONTACT  AND  INFORMATION
Report Sewer ODORS
Report Sewer SPILLS   Or CALL 3-1-1, or (213) 473-3231
More information: (213) 978-0333,